Subcontractor recorded liens on the buildings
Background
Mr. Y runs a window and door company in the San Gabriel Valley with a dozen or so workers. In spring 2025 he took a subcontract to install windows in a developer's three small apartment buildings in Los Angeles County. He finished in November; the developer paid the earlier installments but kept putting off the remaining balance of about $680,000, saying "some windows leak, we'll pay once it's sorted out."
Mr. Y had fronted his workers' wages and the materials himself. He called dozens of times; the developer either didn't answer or said "next month."
Strategy
We looked at the deadlines first. Unpaid construction work can be recorded as a lien on the finished property, but the window after completion is short, and once it closes the right is gone. So in the month he retained us, we recorded liens on all three buildings and then sued the developer for nonpayment within the required time.
We did not dig in on the leak claim. We invited the developer to inspect the site with us; only four windows had faulty sealant, and Mr. Y had them fixed within two days and documented with photos. That left the developer no reason to keep withholding payment.
The liens on the buildings were what really worried the developer. It needed to sell the buildings and pay off its construction loan, and buyers and lenders would not proceed with the liens on title. In August the parties mediated, and the developer agreed to pay in full plus part of the interest.
Case Timeline
| Date | Milestone |
|---|---|
| April 2025 | Subcontract signed; work began |
| Early November 2025 | Windows completed on all three buildings; developer withheld about $680,000 |
| December 2025 | Retained Lingtu Law; liens recorded on all three buildings |
| February 2026 | Sued the developer |
| May 2026 | Joint site inspection; Mr. Y repaired four leaking windows |
| August 2026 | Mediation; developer agreed to pay in full plus interest |
| Late September 2026 | Payment received; liens released and case dismissed |
Outcome
In late September, the balance of about $680,000 plus about $50,000 in interest was paid to Mr. Y. Once the money arrived, we released the liens on the three buildings and dismissed the case.
