Success Stories/Litigation/Civil & Business Litigation/All the Windows in Three Apartment Buildings Were In, but the Developer Held Back About $680,000: A Lien on the Buildings Stalled the Sale, and the Money Came In With Interest
About $680,000 balance paid with interest

Subcontractor recorded liens on the buildings

All the Windows in Three Apartment Buildings Were In, but the Developer Held Back About $680,000

Background

Mr. Y runs a window and door company in the San Gabriel Valley with a dozen or so workers. In spring 2025 he took a subcontract to install windows in a developer's three small apartment buildings in Los Angeles County. He finished in November; the developer paid the earlier installments but kept putting off the remaining balance of about $680,000, saying "some windows leak, we'll pay once it's sorted out."

Mr. Y had fronted his workers' wages and the materials himself. He called dozens of times; the developer either didn't answer or said "next month."

Strategy

We looked at the deadlines first. Unpaid construction work can be recorded as a lien on the finished property, but the window after completion is short, and once it closes the right is gone. So in the month he retained us, we recorded liens on all three buildings and then sued the developer for nonpayment within the required time.

We did not dig in on the leak claim. We invited the developer to inspect the site with us; only four windows had faulty sealant, and Mr. Y had them fixed within two days and documented with photos. That left the developer no reason to keep withholding payment.

The liens on the buildings were what really worried the developer. It needed to sell the buildings and pay off its construction loan, and buyers and lenders would not proceed with the liens on title. In August the parties mediated, and the developer agreed to pay in full plus part of the interest.

Case Timeline

Date Milestone
April 2025 Subcontract signed; work began
Early November 2025 Windows completed on all three buildings; developer withheld about $680,000
December 2025 Retained Lingtu Law; liens recorded on all three buildings
February 2026 Sued the developer
May 2026 Joint site inspection; Mr. Y repaired four leaking windows
August 2026 Mediation; developer agreed to pay in full plus interest
Late September 2026 Payment received; liens released and case dismissed

Outcome

In late September, the balance of about $680,000 plus about $50,000 in interest was paid to Mr. Y. Once the money arrived, we released the liens on the three buildings and dismissed the case.

How much time does your dispute have left?

Litigation and arbitration both have deadlines and procedural milestones, and preparing evidence early strengthens your negotiating position. Send us your contract, correspondence, and letters from the other side. A member of our team will contact you within one business day for a free initial assessment.

Schedule a ConsultationCall 415·547·9999Monday–Friday 9:30–18:00 (Pacific Time)