Partner diverted construction funds
Background
In 2023 Mr. C partnered with Mr. W, a friend from his hometown, to buy land in the San Gabriel Valley and build twelve townhomes. Mr. C put in about $6 million; Mr. W handled the financing, the construction site and the books.
In October 2024 the general contractor suddenly stopped work, saying it had not been paid in three months. Mr. C pulled the bank statements and found that about $16 million in construction loan draws and buyer deposits had been moved by Mr. W into companies he controlled, some used to pay debts on his other project and some to buy two houses. The site sat idle, the bank was pressing on the loan, and more than ten buyers were waiting for their homes.
Strategy
We handled the most urgent things first. In November 2024 we sued Mr. W and asked the court for two orders: freeze the accounts of his affiliated companies, and appoint a neutral receiver to run the project. The reasoning was simple: the money belonged to the partnership, Mr. W was managing it for everyone, and having diverted it to himself he could no longer be trusted with it. At a hearing in late December, the judge granted both.
The receiver negotiated an extension with the bank and got the contractor back to work. On our side, we spent most of a year subpoenaing records bank by bank and mapping where every dollar went: which company it went to and which house it bought. When we deposed Mr. W in July 2025 and put the map in front of him, he could not explain it.
Trial was set for September 2026. At the mandatory settlement conference beforehand, with no way around the evidence, Mr. W agreed to settle: return the cash, transfer the two houses bought with diverted money, and give up his own share of the partnership.
Case Timeline
| Date | Milestone |
|---|---|
| May 2023 | Mr. C and Mr. W formed a partnership to develop twelve townhomes |
| October 2024 | Contractor stopped work; Mr. C found about $16 million had been diverted |
| Mid-November 2024 | Retained Lingtu Law; sued and sought a freeze and a receiver |
| Late December 2024 | Hearing; affiliated companies' accounts frozen and a receiver appointed |
| July 2025 | Bank records completed; Mr. W deposed |
| August 2026 | Settlement reached at the mandatory settlement conference |
| October 2026 | Court approved the settlement; receivership ended and project returned to Mr. C |
Outcome
In October 2026 the court approved the settlement. Mr. C received the cash, the houses and Mr. W's ownership share, worth about $13 million in total. Over the year-plus of receivership the townhomes were finished and most were sold, the project was handed back to Mr. C, and the buyers all received their homes.